March 13, 1997
FOR IMMEDIATE RELEASE
NRC ISSUES CONFIRMATORY ACTION LETTER TO TMI ON EMERGENCY PREPAREDNESS ISSUES
The Nuclear Regulatory Commission staff has issued a letter
to GPU Nuclear Corporation to confirm commitments by the company
to deal with weaknesses revealed during an emergency exercise
held March 5 at the Three Mile Island (TMI) nuclear power plant
in Middletown, Pa.
An NRC team which evaluated the exercise found four exercise
weaknesses: 1) during the drill, the emergency response
organization did not recognize that conditions at the facility
had degraded to the point that it was necessary to declare a
"general emergency"; 2) initially, the response organization
incorrectly evaluated steam generator tube leakage; 3) the
technical analysis of the simulated accident conditions provided
to response organization managers by the technical support staff
was inadequate; and 4) the response organization staff did not
assess the need for protective action recommendations to off-site
officials when dose projections appeared to indicate protective
action guidelines would be exceeded beyond the 10-mile emergency
planning zone.
In a letter to GPU, NRC Region I Administrator Hubert J.
Miller said: "We acknowledge that simulator malfunctions,
exercise controller actions, and scenario planning issues
adversely affected this exercise and raised questions about the
validity of the exercise as a performance measure. Those factors
also precluded our ability to evaluate your actions to correct a
radiation dose assessment weakness from the previous full-participation exercise."
Nevertheless, Mr. Miller added: "Not withstanding the above,
the NRC views the identified weaknesses and problems as important
findings, requiring prompt corrective action."
Those actions are:
1. Initiate immediate corrective actions to address the
four weaknesses and conduct training for the entire emergency
response organization on those actions by April 15.
2. Perform a root cause analysis of the issues associated
with the poor exercise performance by April 15. The analysis
will cover the specific weaknesses along with emergency response
organization training, scenario development, simulator problems,
controller activities, the exercise critique process and recent
staffing changes in emergency preparedness and response.
3. Conduct a remedial on-site exercise by May 15, to test
major portions of the emergency plan that will allow GPU and the
NRC to assess the effectiveness of the utility's corrective
actions regarding the exercise weaknesses and problems.
4. Discuss your proposed corrective actions and any
assessments made to date, in a meeting with NRC staff on March
17. This meeting will be held at the Three Mile Island Training
Center at 10:00 a.m. and will be open for public observation.
5. Provide, at that meeting, and in writing, within 10 days
subsequent to that meeting, GPU's views on the significance of
the exercise weaknesses and problems identified during the
exercise, and why GPU believes that corrective actions taken or
planned will be effective.
Issuance of this confirmatory action letter does not
preclude the NRC from taking enforcement action for violations of
NRC requirements that have prompted the issuance of this letter.