Incident Chronology at Peach Bottom Atomic Power Plant: 1974- 2012
Philadelphia Electric's (PECO) applied for a license to operate the
Peach Bottom Atomic Power Station in late-July, 1960. The application
was approved by the Atomic Energy Commission. Peach Bottom was a 40
megawatt, High Temperature Graphite Moderated reactor that operated
from 1966-1974.
Peach Bottom 2 & 3 , are 1,065 megawatt Boiling Water Reactor designed
by General Electric and engineered by Bechtel. Both reactors began
operation in July, 1974, but had their licensees extended by the Nuclear
Regulatory Commission (NRC) and are expected to operate though 2034.
The Nuclear Regulatory Commission (NRC) and the Institute for
Nuclear Power Operations (INPO) have clearly demonstrated that
Philadelphia Electric's (PECO), renamed Exelon in 2000, performance has
historically been lackadaisical and sub-par. In order to put Peach Bottom's
operating history into perspective, it is necessary to review PECO's plant
legacy.
According to Eric Epstein, Chairman, TMI-Alert: "Managerial
problems further aggravate and compound the inherent flaws with Peach
Bottom's reactor and containment structure." The reactors at Peach
Bottom are General Electric (GE) Boiling Water Reactors (BWR). Epstein
noted, "The GE-BWR is an obsolete design no longer built or constructed.
Many in the industry feel it is inferior to Pressurized Water Reactors.
Obviously the age of the reactors, and the subsequent embrittlement that
ensues, further erode the margin of safety."
Peach Bottom's Mark 1 containment structure has been
demonstrated by Sandia Laboratories to be vulnerable during a core melt
accident. Epstein explained: "The containment is likely to fail during a
core melt accident [like Three Mile Island] allowing radiation to escape
directly into the environment." Nuclear industry officials say the problem
with the Mark 1 is that it is too small and wasn't designed to withstand the
high pressure it is supposed to resist.