Did you catch "The Meltdown: Three Mile Island" on Netflix? TMI remains a danger and TMIA is working hard to ensure the safety of our communities and the surrounding areas. Learn more on this site and support our efforts. Join TMIA. To contact the TMIA office, call 717-233-7897.
NRC Schedules Predecisional Enforcement Conference with BWXT
The Nuclear Regulatory Commission staff will hold a predecisional enforcement conference with officials from BWXT Nuclear Operations Group Inc. on June 21 to discuss two preliminary violations of regulatory requirements that occurred at the Lynchburg, Virginia, fuel fabrication facility in January 2023.
The conference starts at 10 a.m. Eastern time in Suite 800 at the NRC’s Region II Office, Marquis One Tower, 245 Peachtree Center Avenue, NE, in Atlanta. The NRC staff will be available to answer questions from the public after the formal portion of the meeting.
Members of the public can also listen to the meeting by dialing 301-576-2978 and entering the conference number 753930684#.
The preliminary violations of NRC requirements were discovered after a January 19 event when a storage tank at BWXT's Uranium Recovery Facility overflowed, spilling uranium solution onto the floor and into a ventilation system. Two safety controls designed to prevent this failed, increasing the risk of an accidental criticality.
BWXT took immediate corrective actions in the affected area. The event did not endanger the plant workers, the public, or the environment.
A subsequent inspection revealed an apparent breakdown of safety controls designed to prevent an accidental criticality at BWXT's facility. The NRC's inspection findings related to that event are described in a May 5 inspection report.
During the conference, BWXT will have the opportunity to provide its perspective or additional information about the apparent violations. The NRC will review the information provided during the meeting and finalize its enforcement decision in a publicly available document.
All three incidents occurred on the watch of Holtec International, a nuclear equipment manufacturer based in Jupiter, Fla. Though the company until recently had little experience shutting down nuclear plants, Holtec has emerged as a leader in nuclear cleanup, a burgeoning field riding an expected wave of closures as licenses expire for the nation’s aging nuclear fleet.
Over the past three years, Holtec has purchased three plants in three states and expects to finalize a fourth this summer. The company is seeking to profitably dismantle them by replacing hundreds of veteran plant workers with smaller, less-costly crews of contractors and eliminating emergency planning measures, documents and interviews show. While no one has been seriously injured at Oyster Creek, the missteps are spurring calls for stronger government oversight of the entire cleanup industry.
Workers walk past the site of a building demolition at Oyster Creek Nuclear Generating Station in New Jersey. Regulators have documented at least nine violations of federal rules at the plant under Holtec’s ownership. (Sarah L. Voisin/The Washington Post)
In the nearly three years Holtec has owned Oyster Creek, regulators have documented at least nine violations of federal rules, including the contaminated water mishap, falsified weapons inspection reports and other unspecified security lapses. That’s at least as many as were found over the preceding 10 years at the plant, when it was owned by Exelon, one of the nation’s largest utility companies, according to The Post’s review of regulatory records.
Joseph Delmar, a spokesman for Holtec, defended the company’s record, saying it takes safety and security seriously. The recent incidents “are not reflective of the organization’s culture,” he said, adding that the worker who knocked down the power line “did not follow the proper safety protocols.” Delmar said the company has decades of experience building equipment to store nuclear waste and employs veteran plant workers to dismantle reactor sites.
“While the decommissioning organization may seem new, the professionals staffing the company are experienced nuclear professionals with intimate knowledge of the plants they work at,” Delmar said in an emailed statement.
Holtec is, however, pioneering an experimental new business model. During the lifetime of America’s 133 nuclear reactors, ratepayers paid small fees on their monthly energy bills to fill decommissioning trust funds, intended to cover the eventual cost of deconstructing the plants. Trust funds for the country’s 94 operating and 14 nonoperating nuclear reactors now total about $86 billion, according to Callan, a San Francisco-based investment consulting firm.
After a reactor is dismantled and its site cleared, some of these trust funds must return any money left over to ratepayers. But others permit cleanup companies to keep any surplus as profit — creating incentives to cut costs at sites that house some of the most dangerous materials on the planet.
Even after reactors are shut down, long metal rods containing radioactive pellets — known as spent fuel — are stored steps away, in cooling pools and steel-and-concrete casks. Nuclear safety experts say that an industrial accident or a terrorist attack at any of these sites could result in a radiological release with severe impacts to workers and nearby residents, as well as to the environment.
Holtec International opened the 50-acre Krishna P. Singh Technology Campus in Camden, N.J., in 2017. (Sarah L. Voisin/The Washington Post)
The Nuclear Regulatory Commission, the independent federal agency tasked with overseeing safety at nuclear sites, conducts regular inspections during the decommissioning process. But state and local officials say the NRC has failed to safeguard the public from risks at shut-down plants, deferring too readily to companies like Holtec.
“The NRC is not doing their job,” said Sen. Edward J. Markey (D-Mass.), who has pushed the agency to adopt stricter regulations around plant decommissioning. “We need a guaranteed system that prioritizes communities and safety, and we don’t have that right now.”
The NRC’s leadership is divided over the role regulators should play. The agency was created in 1974, as the first generation of commercial reactors was going online, and its rules were mainly designed to safeguard the operation of active plants and nuclear-material sites. As reactors shut down, the NRC began reducing inspections and exempting plants from safety and security rules.
Last November, the NRC approved a new rule that would automatically qualify shut-down plants for looser safety and security restrictions. Christopher T. Hanson, a Democrat nominated by President Donald Trump and promoted to the role of chairman by President Biden, has said the changes would improve the “effectiveness and efficiency” of the decommissioning process.
Commissioner Jeff Baran, also a Democrat, voted against the proposed rule and called for the NRC and local governments to play a bigger role. “Radiological risks remain at shutdown nuclear plants that must be taken seriously,” he cautioned in public comments. Baran added that the agency already takes a “laissez-faire” approach to decommissioning and that the new rule “would make the situation even worse, further skewing the regulation towards the interests of industry.”
Dan Dorman, the NRC’s executive director for operations, said in an email that the agency lifts restrictions at plants only if it determines the plant will continue to be safe. In addition to citing Holtec for violations at Oyster Creek, the agency has required the company to take corrective measures, including external security assessments of all its nuclear sites.
“Our increased oversight and the recent enforcement actions demonstrate our concern about the situation at Oyster Creek,” Dorman said.
The emissions stack at Oyster Creek, which was permanently shut down in 2018. The plant’s single reactor generated enough electricity to power 600,000 homes. (Sarah L. Voisin/The Washington Post)
Holtec faces mounting criticism beyond Oyster Creek. Michigan officials have said they worry Holtec will leave residents on the hook for cleanup costs at the Palisades plant on the shores of Lake Michigan. Massachusetts officials have protested Holtec’s plan to take 1 million gallons of contaminated water from the defunct Pilgrim power plant and dump it into Cape Cod Bay.
While Holtec acknowledges a funding shortfall at Palisades, Delmar says the fund will appreciate in value to cover the cost of the cleanup. At Pilgrim, Holtec has said the potential radiation dose from the Cape Cod release would be farless than the average traveler receives on a typical cross-country flight.
In the Southwest, Holtec has ignited a different controversy. As the company acquires old plants, it is proposing to ship the highly radioactive spent fuel to New Mexico, where it plans to build a storage facility.Gov. Michelle Lujan Grisham (D) has vowed to fight the plan, telling Trump in a 2020 letter that storing radioactive material in the oil-rich Permian Basin region would be “economic malpractice.”
Holtec says it is working in partnership with a group of local officials who believe the benefits of the facility — including new jobs and investment — outweigh the risks. On its website, Holtec says the facility will provide “a safe, secure, temporary, retrievable, and centralized facility for storage of used nuclear fuel and high-level radioactive waste until such time that a permanent solution is available.”
The growing debate marks the latest twist in the tortured saga of nuclear power, which once was hailed as a miracle technology capable of producing large quantities of clean, affordable energy. In the early 1970s, the federal Atomic Energy Commission estimated that about 1,000 reactors would be built in the United States, and that nuclear sources eventually would provideat least half of the world’s power.
But those ambitions soon collided with fears about nuclear radiation, especially after disastrous meltdowns at Chernobyl in Ukraineand Fukushima in Japan. Nuclear energy peaked at around 18 percent of global electricity production in the 1990s and now comprises about 10 percent, according to the U.S. Energy Information Association.
Reactors in the United States initially were licensed for 40 years, and most were renewed for another 20 years. Of 94 reactors that are still active, licenses at over half are set to expire in the next two decades, according to Julia Moriarty, a senior vice president at Callan.
Recently, worries about climate change have led some governments to embracenuclear as a low-carbon source of power. Biden has called nuclear essential to the nation’s climate goals, and Washingtonlast year set aside $6 billion for extending the licenses of some plants and $2.5 billion fordeveloping new nuclear technologies.
But the nation continues to puzzle over the problem of nuclear waste. This material, which emanates invisible but harmful radiation for hundreds of years, is stored in protective containers on the grounds of nuclear plants, scattered in dozens of towns across the country. A plan to build a national waste repository in Nevada’s Yucca Mountain stalled amid decades of political gridlock, leaving these towns saddled indefinitely with the threat of an accidental release or terrorist attack.
Holtec is approaching those communities with an offer to clean up the mess.
NRC Identifies Nine Abnormal Occurrences in FY 2022 Annual Report to Congress
The Nuclear Regulatory Commission has published its annual report to Congress for fiscal year 2022 on abnormal occurrences involving medical and industrial uses of radioactive material.
Nine abnormal occurrences were identified, seven of which were medical events, such as misadministration of radioactive material during diagnostic procedures or the treatment of an illness. The other two events were non-medical overexposures. No events at commercial nuclear power plants in FY 2022 met the criteria for an abnormal occurrence.
An abnormal occurrence is defined as an unscheduled incident or event that the NRC determines to be significant from the standpoint of public health or safety. The FY 2022 report did not identify any event that met the guidelines for inclusion as “other events of interest.” The report includes an update to an FY 2021 abnormal occurrence at the National Institute of Standards and Technology Center for Neutron Research.
The “Report to Congress on Abnormal Occurrences, FY 2022” is available on the NRC website.
From home energy retrofits and rooftop solar to wind energy and battery storage, we have more and better ways than ever before to transform our energy systems away from fossil fuels.
This June 2, 2016 file photo shows Exelon Corporation’s Clinton Power Station through a tangle of high-voltage power lines in Clinton, Illinois.
AP Photos
A growing chorus in Washington equates weaning our country off energy from killer fossil fuels to relying more heavily on new nuclear power plants. The same debates are happening in state capitals from Richmond to Raleigh, Springfield to Sacramento.
This chorus distracts from the real work ahead of ensuring clean, renewable, affordable energy for every community.
The risk of nuclear energy is an easy dividing line. To opponents, names like Three Mile Island, Chernobyl and Fukushima are all the evidence we need that a catastrophic event is unavoidable and unacceptable. For supporters, those events are a sign that disasters are few. Both are right: They happen infrequently, and when they do occur, they are cataclysmic.
The more compelling reasons we should drop the silver bullet thinking about nuclear power are its cost and its reliability.
Since the mid-20th century when nuclear power entered the public imagination, the belief has been that energy is “free” — start the chain reaction, make electricity. But it’s not free, and it never has been; uranium must be mined, and reactor fuel is consumable. We’ve reached a point where renewable sources like wind and solar power are cheaper, in part because they are quicker to come online.
Nuclear power: more costly, vulnerable to climate change
Lazard, a global investment bank and financial consultancy that reports annually on the “levelized cost of energy” from various sources, found that nuclear power is two to six times more costly per megawatt hour than wind and solar, which now cost the same per megawatt hour. The capital cost of large-scale solar and wind is at least eight times lower.
The time to get new wind and solar into the electricity grid is at least half the time for a new nuclear plant; history shows anyone who estimates the completion date for a new nuclear plant is wrong.
Unlike most industries that rely heavily on science and technology, the cost of building nuclear plants is rising over time. In Silicon Valley, they call it a reverse learning curve.
Supporters of nuclear power like to argue that nuclear plants are required for reliability, and that they can operate all the time.
This ignores nuclear’s vulnerability to climate change: severe weather, extreme temperatures, and both floods and droughts have forced nuclear plants to shut down unexpectedly in recent years.
Additionally, a reactor goes offline for routine maintenance at least every two years, which means a plant must have more total capacity to cover that maintenance routine.
By comparison, wind and solar farms have much fewer operational problems. And battery backups have gotten faster than the gas power generation that nuclear plants often turn to meet peak demand.
It’s time to confront nuclear’s challenges — uranium mining, accident risk, cost and climate vulnerability — and double down on the solutions we know will be central to our shift away from fossil fuels.
We can’t afford the distraction of a fiction around nuclear power when burning fossil fuels threatens the health of millions around the world annually. Our focus must be on bringing the clean air, cost savings and economic benefits of clean energy to communities across the country as quickly as we can.
From home energy retrofits and rooftop solar to wind energy and battery storage, we have more and better ways than ever before to transform our energy systems from fossil fuels to energy that’s actually clean, reliable and renewable.
Ben Jealous is executive director of the Sierra Club and a professor at the University of Pennsylvania.
Hanford’s Waste Treatment and Immobilization Plant. (Photo: DOE)
A pair of recent reports by the U.S. Government Accountability Office and the National Academies of Science, Engineering, and Medicine highlight some of the challenges the Department of Energy faces in treating the millions of gallons of legacy radioactive waste at the Hanford Site in Washington state.
Both reports focus on recent efforts by the DOE to assess possible alternatives to vitrifying Hanford’s 54 million gallons of liquid tank waste, immobilizing it in a solid glass form. The DOE has long intended to vitrify all the tank waste after separating it into high- and low-level radioactive waste streams. That plan, however, may not be feasible, as the DOE continues to face technical problems, cost overruns, and schedule delays with building the site’s Waste Treatment and Immobilization Plant (WTP).
The issues: According to the GAO, construction of the WTP’s Pretreatment Facility, which would separate the waste streams, and High-Level Waste Facility, which would vitrify the HLW, cannot be completed as planned due to technical issues. Completing the facilities as planned, the GAO said, would be cost and schedule prohibitive.
Likewise, the WTP’s Low-Activity Waste Facility, which is currently being commissioned, does not have the capacity to vitrify all of Hanford’s LLW, and the DOE is seeking alternatives for treating the remaining waste, referred to as supplemental low-activity waste (SLAW). The DOE is currently reviewing the possibility of solidifying Hanford’s SLAW in grout and disposing of it on site, at an outside facility, or a combination of both.
The DOE is also negotiating with the Washington State Department of Ecology and the Environmental Protection Agency on revising court-mandated deadlines for treating Hanford’s tank waste.
High-level waste: The GAO report, Hanford Cleanup:DOE Should Validate its Analysis of High-Level Waste Treatment Alternatives, assesses the DOE’s consideration of 24 options for treating Hanford’s HLW. Those options were outlined in an analysis of alternatives report released by the DOE in January. The analysis also found that the life-cycle cost estimates for treating the HLW ranged from $135 billion to $5 trillion.
While the DOE plans to select an alternative for HLW treatment in the near future, the GAO found that the DOE has not committed to validating its analysis of alternatives. “Given the enormous cost and schedule implications of the decision, it is essential for DOE to take steps now to provide assurance that all viable alternatives for optimizing the tank waste treatment mission are considered,” the GAO said in its report.
The DOE agreed with the GAO’s recommendation to obtain an independent review of the department’s analysis of HLW treatment alternatives, adding that actions the department has and will take satisfy the recommendation. The GAO, however, said it believes further action is needed.
The FFRDC selected four alternative approaches to treating the SLAW, with a baseline alternative of vitrification with disposal at Hanford’s on-site disposal facility. The three other alternatives include solidification through steam reforming (similar to that of Idaho’s Integrated Waste Treatment Unit) with on-site disposal, off-site grouting and disposal, and a phased approach that begins with off-site grouting and disposal and transitions to on-site operations.
According to the NASEM, the FFRDC has made a strong technical case that off-site grouting and disposal is for the most part the preferred option, and may be a technically valid option with on-site disposal if found acceptable from a waste acceptance standpoint.
The NASEM also found that “a clear and persistent difference exists” between grouting and vitrification and steam reforming, and that grouting “dominates the other two alternatives on the basis of lower cost and shorter time to operational startup”.
Before reaching a decision on specific alternatives, the NASEM said that a detailed analysis will still be needed for a wider variety of grouting options. This includes the location of grouting plants, the possibility of on-site commercial SLAW facilities, and a detailed assessment of the waste acceptance criteria, cost, and other aspects of off-site treatment or disposal, including regulatory and public acceptance.
[A study published in the Proceedings of the National Academy of Sciences (PNAS) in May 2022 indicates that small modular reactors (SMRs) – nuclear reactors designed to produce <300 megawatts (MW) of electricity – are likely to exacerbate the challenges of nuclear waste management and disposal. (Krall et al, 2022) The study, coauthored by Lindsay M. Krall and Rodney C. Ewing of the Center for International Security and Cooperation at Stanford University and Allison M. Macfarlane, of the School of Public Policy and Global Affairs at University of British Columbia Vancouver, a former Chair of the US Nuclear Regulatory Commission (NRC).
Developers, vendors and others touting SMRs and other “advanced” reactors claim that they will create less spent nuclear fuel (SNF) or high-level waste (HLW) than traditional 1,000 MW pressurized water reactors (PWRs), the prevalent type of reactor in commercial operation today. However the promoters “often employ simple metrics, such as mass or total radiotoxicity” to support their claims.
About 30 of the 70 SMR designs listed in the International Atomic Energy Agency (IAEA) Advanced Reactors Information System are characterized as “‘advanced’” reactors, which would use non-water coolants (e.g., helium, liquid metal, or molten salt).
For this study, Krall et al estimated the amount and characterized the nature of the nuclear waste from 3 distinct proposed SMR designs championed as advanced under development by NuScale, Terrestrial Energy, and Toshiba. The designs, respectively, involve proposed water-cooled, molten salt–cooled, and sodium-cooled SMRs. Krall et al analyzed the energy-equivalent volume, radio-chemistry, decay heat, and fissile isotope composition of spent fuel, high-level waste (HLW), and low- and intermediate-level (LILW) low-level waste streams. Their calculations indicate the SMRs are likely to “produce more voluminous and chemically/physically reactive waste” than traditional light water reactors.
Specifically the research group’s calculations indicate SMRs may generate 2 to 30 times more radioactive waste in need of management and disposal than conventional reactors per unit energy extracted.
Although the Krall analysis focuses on only 3 of dozens of proposed SMR designs, it advances that intrinsically higher levels of neutron leakage (causing activation of reactor materials) associated with SMRs suggests that most designs are inferior to traditional commercial reactors with respect to the generation, management, and final disposal of nuclear waste.
“This increase of volume and chemical complexity will be an additional burden on waste storage, packaging, and geologic disposal. Also, SMRs offer no apparent benefit in the development of a safety case for a well-functioning geological repository.”
The finding of additional waste volume is attributed to the use of neutron reflectors and/or of chemically reactive fuels and coolants in SMR designs.
Moreover, the volume of waste and energy-equivalent volume of waste are not the only important evaluation metrics. “Nuclear reactors generate several distinct waste streams, which contain variable concentrations of radionuclides that have a range of half-lives from hours to millions of years and a variety of very different nuclear and chemical properties.” The radionuclide composition and speciation are “important parameters” for consideration of nuclear waste disposal in a geologic repository.
In the analysis, Krall et al note that management and disposal of SNF or HLW must take into account metrics beyond mass, volume, or radioactivity and consider: “ • the chemistry of the SNF matrix and its radionuclide contents, which influences the environmental mobility of radionuclides and their consequent potential to deliver radiation doses to humans in the biosphere; • the heat generated by radioactive decay, which can damage the SNF matrix, as well as other components of the barrier system (e.g., the stability of backfill clays used to inhibit radionuclide transport); and • the concentrations of fissile isotopes in the SNF, which influence its potential to sustain a heat-generating critical chain reaction that can damage the fuel and barrier systems in a geologic repository .”
“These variables depend on the SNF radiochemical composition (i.e., the radionuclide amount and type, including their chemical properties, half-lives, decay modes, and daughter products), which in turn, depends on the initial fuel composition, its final burnup, and the time elapsed since it was discharged from the reactor. In addition, the in-core neutron energy spectrum affects the types and amounts of radionuclides formed in the fuel and reactor materials, such that the composition of SNF generated by a moderated thermal-spectrum reactor will differ from that generated by a fast reactor.”
The specifics of waste chemistry is also relevant for determination of how any particular nuclear material may be stored. Proposed SMRs “employ chemically exotic fuels and coolants (e.g., metallic sodium, metallic uranium, and uranium tetrafluoride) that react rapidly with water and/or atmospheric oxygen.” Experience with the handling and disposing of these chemically unstable waste streams is limited.
Krall et al add that exotic spent fuel, coolant, and/or moderator materials will require treatment and conditioning prior to disposal, but, as the properties of the by-products and infrastructure associated with such processes are uncertain, the additional waste streams generated by treatment and conditioning processes are not addressed in this study.
Krall et al conclude:
“This analysis of three distinct SMR designs shows that, relative to a gigawatt-scale PWR, these reactors will increase the energy-equivalent volumes of SNF, long-lived LILW, and short-lived LILW by factors of up to 5.5, 30, and 35, respectively. These findings stand in contrast to the waste reduction benefits that advocates have claimed for advanced nuclear technologies. More importantly, SMR waste streams will bear significant (radio-)chemical differences from those of existing reactors. Molten salt– and sodium-cooled SMRs will use highly corrosive and pyrophoric fuels and coolants that, following irradiation, will become highly radioactive. Relatively high concentrations of 239Pu and 235U in low–burnup SMR SNF will render recriticality a significant risk for these chemically unstable waste streams.”
“SMR waste streams that are susceptible to exothermic chemical reactions or nuclear criticality when in contact with water or other repository materials are unsuitable for direct geologic disposal. Hence, the large volumes of reactive SMR waste will need to be treated, conditioned, and appropriately packaged prior to geological disposal. These processes will introduce significant costs—and likely, radiation exposure and fissile material proliferation pathways—to the back end of the nuclear fuel cycle and entail no apparent benefit for long-term safety.
Although we have analyzed only three of the dozens of proposed SMR designs, these findings are driven by the basic physical reality that, relative to a larger reactor with a similar design and fuel cycle, neutron leakage will be enhanced in the SMR core. Therefore, most SMR designs entail a significant net disadvantage for nuclear waste disposal activities. Given that SMRs are incompatible with existing nuclear waste disposal technologies and concepts, future studies should address whether safe interim storage of reactive SMR waste streams is credible in the context of a continued delay in the development of a geologic repository in the United States.”]
NuScale and the Utah Associated Municipal Power Systems (UAMPS) announced costs of a 462-megawatt small modular reactor (SMR) have risen dramatically.
As recently as mid-2021, the target price for power was pegged at $58 per megawatt-hour (MWh); it’s risen to $89/MWh, a 53% increase.
The price would be much higher without $4 billion federal tax subsidies that include a $1.4 billion U.S. Department of Energy contribution and a $30/MWh break from the Inflation Reduction Act.
The higher target price is due to a 75% increase in the estimated construction cost for the project, from $5.3 to $9.3 billion dollars.
From 2016 to 2020, they said the target power price was $55/megawatt-hour (MWh). Then, the price was raised to $58/MWh when the project was downsized from 12 reactor modules to just six (924MW to 462MW). Now, after preparing a new and much more detailed cost estimate, the target price for the power from the proposed SMR has soared to $89/MWh.
Remarkably, the new $89/MWh price of power would be much higher if it were not for more than $4 billion in subsidies NuScale and UAMPS expect to get from U.S. taxpayers through a $1.4 billion contribution from the Department of Energy and the estimated $30/MWh subsidy in the Inflation Reduction Act (IRA).
It also is important to remember that the $89/MWh target price is in 2022 dollars and substantially understates what utilities and their ratepayers actually will pay if the SMR is completed. For example, assuming a modest 2% inflation rate through 2030, utilities and ratepayers would pay $102 for each MWh of power from the SMR—not the $89 NuScale and UAMPS want them to believe they will pay.
The 53% increase in the SMR’s target power price since 2021 has been driven by a dramatic 75% jump in the project’s estimated construction cost, which has risen from $5.3 billion to $9.3 billion. The new estimate makes the NuScale SMR about as expensive on a dollars-per-kilowatt basis ($20,139/kW) as the two-reactor Vogtle nuclear project currently being built in Georgia, undercutting the claim that SMRs will be cheap to build.
NuScale and UAMPS attribute the construction cost increase to inflationary pressure on the energy supply chain, particularly increases in the prices of the commodities that will be used in nuclear power plant construction.
For example, UAMPS says increases in the producer price index in the past two years have raised the cost of:
Fabricated steel plate by 54%
Carbon steel piping by 106%
Electrical equipment by 25%
Fabricated structural steel by 70%
Copper wire and cable by 32%
In addition, UAMPS notes that the interest rate used for the project’s cost modeling has increased approximately 200 basis points since July 2020. The higher interest rate increases the cost of financing the project, raising its total construction cost.
Assuming the commodity price increases cited by NuScale and UAMPS are accurate, the prices of building all the SMRs that NuScale is marketing—and, indeed, of all of the SMR designs currently being marketed by any company—will be much higher than has been acknowledged, and the prices of the power produced by those SMRs will be much more expensive.
Finally, as we’ve previously said, no one should fool themselves into believing this will be the last cost increase for the NuScale/UAMPS SMR. The project still needs to go through additional design, licensing by the U.S. Nuclear Regulatory Commission, construction and pre-operational testing. The experience of other reactors has repeatedly shown that further significant cost increases and substantial schedule delays should be anticipated at any stages of project development.
The higher costs announced last week make it even more imperative that UAMPS and the utilities and communities participating in the project issue requests for proposal (RFP) to learn if there are other resources that can provide the same power, energy and reliability as the SMR but at lower cost and lower financial risk. History shows that this won’t be the last cost increase for the SMR project.
David Schlissel (dschlissel@ieefa.org) is IEEFA director of resource planning analysis
"This is nuts:" European power prices go negative as springtime renewables soar | RenewEconomy California prices are in negative territory this morning. The Spring brings this out – solar production is high, loads are low. Add some wind, and you have a glut.
In the US, this is compounded by the production tax credit for earlier wind products. Producers receive 1.9 cents/kwh when they produce. So they continue producing when the price goes negative. This is devastating for nuclear, as it does not have the flexibility to follow the market.
In the Pacific Northwest, we have an interesting twist on this. During the “fish flush” season, when juvenile salmon need to get to the ocean by the time their bodies evolve to salt water species, we have to run hydro through the turbines. We cannot spill too much of it over the top, as that results in nitrogen supersaturation of the water, which can contribute to gas bubble disease in the juveniles.
But, the article that Arnie sent, with prices predicted to go to -235 Euro/MWh, is really quite extraordinary.
Balmy springtime weather across Europe and growing renewable energy capacity has led to multiple days of negative wholesale power prices across the continent, highlighting the need for increased energy storage capacity.
A number of factors have led to consistent negative wholesale power prices across Europe over the last few weeks. Energy analyst Gerard Reid has been highlighting these trends stemming not only from increased renewables and favourable weather conditions, but also the impediment to stable generation levels caused by nuclear power.
For example, according to Reid, Denmark “consistently meets 85% of its weekly energy needs from renewables. However, on particularly windy days … Denmark’s strong interconnections with neighbouring countries enable it to export up to 50% of excess power.
“This demonstrates the benefits of interconnection, but it also reveals the limitations when considering the current situation of excess power across Europe.
“Countries like Spain, France, the Netherlands, Germany, Denmark, and Sweden are experiencing zero or negative prices due to surplus production as they have reached the limit of what they can use or even export.”
Reid followed this up a week later, explaining that wholesale power prices dropping to zero or negative in the Nordics “stems from substantial snow melt in Norway, Sweden, and Finland, fuelling hydro turbines and generating large amounts of electricity.”
MetDesk meteorologist Theo Gkousarov concurred, explaining how the recent weather conditions have led to negative prices.
“An area of high pressure dominating across much of central and north-west Europe” resulted in ‘lots of solar power generation across the area,” he said.
Similarly, in Finland, “an oversupply of hydroelectric power” resulted from “excessive springtime meltwater”.
But it is not just the weather that is delivering abundant renewables, while also making life difficult for network operators.
“Additionally, the inflexibility of nuclear power exacerbates the situation, as it’s difficult to adjust its output,” explained Reid.
“Furthermore, the region witnessed the addition of new generation capacity last year, including 5 GW of wind power and the Olkiluoto 3 nuclear reactor in Finland, boasting a capacity of 1.6 GW.
“Simultaneously, weak power demand in the Nordics, primarily due to Sweden’s weak economic environment, compounds the issue of oversupply. Consequently, the least flexible generators, such as run-of-the-river hydro and nuclear plants, incur costs to offload excess power.”
Reid and Gkousarov both highlighted the recent price volatility of wholesale power prices across Europe that has been seen over the last 10 days.
Over the weekend in Europe, negative wholesale prices hit across a huge portion of Europe, with prices rising from negative by on average EUR100 per MWh when the sun set.
On Sunday, power prices in the Netherlands were expected to hit negative EUR235/MWh, while prices in Germany at lunchtime hit -EUR129/MWh.
As Reid put it: “This is nuts.”
The problem is that companies are having to pay to offload excess electricity generated due to the inflexibility in the systems.
And while long-term solutions, according to Reid, include “building more pumped hydro storage … upgrading existing hydro facilities … increasing flexible demand … building out grid infrastructure,” the immediate solution is short-term batteries.
“Batteries are destined to become integral components of our power systems in the future,” said Reid.
“The pressing question is whether traditional power generators can act swiftly enough to avoid losses from generating and selling electricity below their operating costs.”